如何使用剪板机折弯机?


 
1、首先是接通电源,在控制面板上打开钥匙开关,再按油泵启动,这样你就听到油泵的转动声音了。(此时机器不动作)
1, the first is the power, in the control panel to open the key switch, and then press the pump to start, so you will hear the sound of the oil pump. (the machine does not move at this time)
2、行程调节,剪板机折弯机使用必须要注意调节行程,在折弯前要试车。折弯机上模下行至很靠下部时必须保证有一个板厚的间隙。否则会对模具和机器造成损坏。行程的调节也是有电动快速调整和手动胃调。
2, stroke adjustment, plate bending machine bending machine use must pay attention to adjust the trip, in the bending before the test must be. The upper die down to the bottom of the bending machine must ensure that there is a gap between the thickness of the plate. Otherwise it will cause damage to the mold and machine. Stroke adjustment is also a fast electric adjustment and manual adjustment of the stomach.
3、折弯槽口选择,一般要选择板厚的8倍宽度的槽口。如折弯4mm的板料,需选择32左右的槽口。
3, bending notch, notch in general to choose the thickness 8 times the width of the. Such as plate bending 4mm, need to choose about 32 slot.
4、后挡料调整一般都有电动快速调整和手动微调,方法同剪板机。
4, after the adjustment of the material is generally electric fast adjustment and manual adjustment, the same method with plate cutting machine.
5、踩下脚踏开关开始折弯,剪板机折弯机与剪板机不同,可以随时松开,松开脚剪板机折弯机便停下,在踩继续下行。
5, step on the foot switch to start bending, shear bending machine and plate shearing machine is different, can be at any time to loosen, loosen the foot plate shear bending machine will stop, continue down on the step.
剪板机折弯机在调试之前要做好以下准备工作,以免机器出现不可挽回的损坏,切记!
Shear machine bending machine prior to commissioning must be prepared to do the following work, to avoid the emergence of machine irreparable damage, remember!
(1)操作者在试车前必须详细阅读本说明书,熟悉机器的主要结构、性能和使用方法。
(1) the operator must read the instruction carefully before commissioning and be familiar with the main structure, performance and usage of the machine.
(2)往油箱内注入32#-16#液压油,油面达到油标线。
(2) injection of 32#-16# hydraulic oil into the oil tank, oil to oil line.
(3)接通电源起动油泵电机,观察电机转向是否正确。
(3) switch on the power supply to start the oil pump motor, and observe whether the motor turn is correct.
(4)松开远程调压阀的手柄(试车时再逐步提高系统的压力)。
(4) loosen the handle of the remote pressure regulating valve (and then gradually increase the pressure of the system during commissioning).
(5)将转换开关旋到“点动”位置,首先由“点动”开始进行试运行。
(5) to switch to the "point" position, first by the "point" to start the test run.